2012 California Construction Law Update – Part 2
Part 2 of my 2012 California Construction Law Update discusses several new laws which are intended to provide relief to the state’s hard hit construction industry, provide for speedier progress payments, place caps on public works retention, establish new requirements for the filing of payment bond claims and limit the types of indemnity that can be required of downstream contractors and subcontractors:
Progress Payments
Beginning January 1, 2012, prime contractors on both public and private projects must pay progress payments to subcontractors no later than 7 days after receipt from the owner. Previously, progress payments were required to be made no later than 10 days after receipt. Prime contractors who fail to make progress payments within 7 days are subject to penalties of 2% per month, disciplinary action and attorney’s fees.
Public Works Retention
Beginning January 1, 2012, for public works contracts entered on or after January 1, 2012 and through January 1, 2016, public owners, original contractors and subcontractors may not withhold more than 5% retention with two exceptions: (1) where an original contractor requires performance and payment bonds in their request for bids and a subcontractor is unable or refuses to furnish performance and payment bonds, the original contractor may withhold retention from that subcontractor in excess of 5% or (2) where the director of the department contracting for the public works makes a finding, prior to bidding the project, that the project is substantially complex and requires the withholding of more than 5% retention. The new law does not change existing law, which permits public owners to withhold up to 150% of any disputed work.
Payment Bonds
Beginning January 1, 2012, for construction contracts entered into on or after January 1, 2012, payment bond claimants who do not have a direct contractual relationship with the original contractor and who did not serve a 20-day preliminary notice may still pursue such claims by giving written notice to the payment bond surety and bond principal. Notice must be given within 15 days after recordation of a notice of completion or, if no notice of completion is recorded, within 75 days after project completion. The new law, which applies to both public and private projects, does not apply to:
(1) Laborers;
(2) Claimants who supplied labor and/or materials to a subcontractor who has a direct contractual relationship with an original contractor who has been paid all progress payments except amounts disputed in good faith; or
(3) Claimants who supplied labor and/or materials to a subcontractor who had a direct contractual relationship with an original contractor who has been terminated but who has been paid all progress payments except amounts disputed in good faith.
These three types of claimants must serve a 20-day preliminary notice in order to make a claim against an original contractor’s payment bond.
The new law is intended to protect original contractors who may not know the identity of second-tier and lower subcontractors and materialmen who provided labor and/or materials on a project and who did not serve a 20-day preliminary notice, but who could nonetheless make a claim on the original contractor’s payment bond.
Indemnity
Beginning January 1, 2013, for commercial construction contracts and public works contracts and amendments entered into on or after January 1, 2013, “Type I” indemnity provisions – in which a downstream contractor or subcontractor is required to indemnify and/or defend an owner or upstream contractor against liability caused by the owner or upstream contractor’s “active negligence or willful misconduct,” for design defects, or for claims that do not arise out of the scope of work performed by the downstream contractor or subcontractor – are void and unenforceable. The new law will apply irrespective of choice-of-law provisions purporting to apply the law of another state and irrespective of any provision in the contract purporting to waive the new law. However, the new law does not apply to residential construction contracts (in which Type I indemnity provisions are already prohibited), contracts with design professionals, Owner Controlled Insurance Programs (OCIPs) and contracts with owner-builders.
It may seem early to begin thinking about 2013 changes, but owners, contractors and subcontractors should carefully review the indemnity provisions in their form contracts this year. If they include Type I indemnity provisions subject to the new law, these provisions will become void and unenforceable beginning January 1, 2013, which may have the effect of leaving them with no indemnity provisions at all.
One Response to “2012 California Construction Law Update – Part 2”
[…] payment laws (but not all of them) and recodified them under new statutory sections, yet only amended (without eliminating) other prompt payment laws. So, If you’re confused, and who could blame you, […]