DSA Announces New Project Certification Process Which Takes Effect August 1, 2014

DSA2If you’re a design professional, project inspector, or public entity involved in the design or construction of K-12 or community college facilities then you’ll be interested in the following announcement from the California Division of the State Architect (“DSA”) regarding its new project certification process which takes effect August 1, 2014 (that’s this Friday folks!):

*****

Are You Ready?

Effective August 1, 2014, California’s Division of the State Architect (DSA) is implementing a new project certification process. Project certification will be achieved through the timely submission of required project documents. To emphasize the importance of the timely submission of documents, DSA reminds all design professionals, inspectors, laboratories, school districts, community colleges, governing boards, and staff that certification starts when construction begins.

The new certification process will include:

  • Elimination of the “90-day Closing Letter.”
  • Requiring certain documents to be submitted during the certification process rather than at the end: failure to submit required documents may result in a stop work order.
  • When a project becomes occupied, in use, or otherwise complete, DSA will review the project file.
  • If the project file is not complete, a deficiency list will be generated and sent to the district and the design professional in general responsible charge.
  • District and design professionals will have 60 days to address outstanding items on the deficiency list.
  • After 60 days, if the project cannot be certified, DSA will issue an updated deficiency list to the district, and the project will be classified as an uncertified project.
  • All uncertified projects are searchable by the public in DSA’s CertificationBox.
  • To certify an uncertified project, the project must be reopened.
  • Additional fees may be required to reopen projects.

Again, this process change commences August 1, 2014. Official procedural documents outlining the new process and forms will be posted to DSA’s webpage as they are made available. For more information, please visit www.dgs.ca.gov/DSA.

*****

The DSA has issued PR 13-02 – Procedure: Project Certification Process – which describes the new project certification process. In addition, California State Architect, Chester A. Widom, FAIA, will be speaking at a workshop sponsored by the Coalition for Adequate School Housing (“CASH”) in Ontario, California this Friday, August 1, 2014 from 8:30 a.m. to 3:00 p.m. to discuss the new project certification process and other changes at the DSA. Further information on the workshop can be found on CASH’s website.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Basic HTML is allowed. Your email address will not be published.

Subscribe to this comment feed via RSS

%d bloggers like this: